earthconnect has commenced Construction of Stage 2, on a Western NSW Manufacturing Facility

 

The Project has reached the second milestone with Racking / Cable Tray completed, and String and Return Wiring is well advanced.

 

Stage 2 is 8.0MW DC (approx. 20,800 Solar Panels) and when completed, and combined with Stage 1, it will have a 10.0MW DC Rating.

 

Once the System enters Revenue Service, it will be Australia’s Largest Roof Mount Solar Energy System.