earthconnect have completed the Critical Design Review and submitted the Application for Connection for a 7.85MWp DC Solar Farm.
The Statement of Environmental Effects has been completed, along with the associated Environmental and Biodiversity Assessment, Aboriginal Heritage Impact Assessment and DPI Water Studies.
All relevant documentation has been submitted to the Local Authority, ready for submission to the Joint Regional Planning Panel (JRPP) and DNSP Network Authority.
It is envisaged that the Project will be approved for construction towards the end of 2020.