earthconnect has commenced Construction of Stage 2, on a Western NSW Manufacturing Facility.

The Project has seen 90% of approximately 20,800 Solar Modules laid, with DC Commissioning to commence shortly.

The Project is running on schedule and within budget, considering signification time constraints caused by inclement weather and the effects of the pandemic.

Stage 2 is 8.0MW DC and when completed, and combined with Stage 1, will have 10.0MW DC Rating.

Once the System enter Revenue Service, it will be Australia’s Largest Roof Mount Solar Energy System.