earthconnect have reached a significant Milestone at the Hunter Solar Farm, and have completed;

  • Driving of Schletter Piles
  • Construction of the Schletter Array Tables
  • Placement of 380w Solar Modules

Quality Assurance shall continue throughout June, and Electrical Works shall commence early July 2019.